Urban Cable Routing on Case-4
8,029.18Mean Cost (Million CNY)L-MVNS
Evaluation Results
| Method | Links | |||
|---|---|---|---|---|
| L-MVNSNumber of independent runs=10, Neighborhood size=10 per operator (30 total), Maximum iterations=6002025.12 | 8,029.18 | 646.54 | 0 | |
| MVNSNumber of independent runs=10, Neighborhood size=10 per operator (30 total), Maximum iterations=6002025.12 | 8,043.41 | 4,306.97 | 0.18 | |
| SNS-1Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 8,193.06 | 4,232.74 | 2.04 | |
| SNS-2Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 8,248.72 | 4,555.78 | 2.73 | |
| SNS-3Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 8,433.52 | 14,282.3 | 5.04 | |
| HGSNumber of independent runs=102025.12 | 11,386.6 | 0 | 41.82 | |
| MCWSNumber of independent runs=102025.12 | 16,020.2 | 0 | 99.52 |