Urban Cable Routing on Case-1
2,481.42Mean Cost (Million CNY)MVNS
Evaluation Results
| Method | Links | |||
|---|---|---|---|---|
| MVNSNumber of independent runs=10, Neighborhood size=10 per operator (30 total), Maximum iterations=6002025.12 | 2,481.42 | 4,027.43 | 0 | |
| L-MVNSNumber of independent runs=10, Neighborhood size=10 per operator (30 total), Maximum iterations=6002025.12 | 2,489.23 | 16.67 | 0.31 | |
| SNS-3Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 2,535.95 | 2,782.67 | 2.2 | |
| SNS-1Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 2,559.75 | 1,786.28 | 3.16 | |
| SNS-2Number of independent runs=10, Neighborhood size=30, Maximum iterations=6002025.12 | 2,582.91 | 3,015.25 | 4.09 | |
| HGSNumber of independent runs=102025.12 | 3,244.4 | 0 | 30.75 | |
| MCWSNumber of independent runs=102025.12 | 3,787.8 | 0 | 52.65 |