# Process-Aware Procurement Lead Time Prediction for Shipyard Delay Mitigation

Source: [Process-Aware Procurement Lead Time Prediction for Shipyard Delay Mitigation](<https://www.sota2.com/research/paper/6979980ca2b28e761d87cba8>)

Collection index: [llms.txt](<https://www.sota2.com/research/llms.txt>)

Data updated: 2026-01-29T05:00:05.136Z

Authors: Yongjae Lee, Eunhee Park, Daesan Park, Dongho Kim, Jongho Choi, Hyerim Bae

Published: 2026-01-27T07:37:11.000Z

## Abstract

Accurately predicting procurement lead time (PLT) remains a challenge in engineered-to-order industries such as shipbuilding and plant construction, where delays in a single key component can disrupt project timelines. In shipyards, pipe spools are critical components; installed deep within hull blocks soon after steel erection, any delay in their procurement can halt all downstream tasks. Recognizing their importance, existing studies predict PLT using the static physical attributes of pipe spools. However, procurement is inherently a dynamic, multi-stakeholder business process involving a continuous sequence of internal and external events at the shipyard, factors often overlooked in traditional approaches. To address this issue, this paper proposes a novel framework that combines event logs, dataset records of the procurement events, with static attributes to predict PLT. The temporal attributes of each event are extracted to reflect the continuity and temporal context of the process. Subsequently, a deep sequential neural network combined with a multi-layered perceptron is employed to integrate these static and dynamic features, enabling the model to capture both structural and contextual information in procurement. Comparative experiments are conducted using real-world pipe spool procurement data from a globally renowned South Korean shipbuilding corporation. Three tasks are evaluated, which are production, post-processing, and procurement lead time prediction. The results show a 22.6% to 50.4% improvement in prediction performance in terms of mean absolute error over the best-performing existing approaches across the three tasks. These findings indicate the value of considering procurement process information for more accurate PLT prediction.

## Recorded benchmark results

A research result applies to its stated dataset, split, metric and evaluation configuration. Compare like-for-like settings, preserve the metric's unit and direction, and distinguish paper-reported results from independent reproduction. The best result recorded here is not a claim of exhaustive, current global coverage.

- [Lead Time Prediction on Shipyard pipe spool dataset](<https://www.sota2.com/research/sota/lead-time-prediction-on-shipyard-pipe-spool-dataset.md>): Lead Time Prediction; Shipyard pipe spool dataset; MAE: 1.66.